Which of the following best describes 'general conditions costs'?

Study for the Construction Cost Estimation and Bid Package Management exam in civil engineering. Prepare with quizzes featuring multiple choice questions. Gain a deeper understanding of construction cost estimation and bid package management to excel in your exam!

General conditions costs encompass the expenses necessary for the overall management and coordination of a construction project, as well as the infrastructure and temporary facilities required to support the project. These costs are not directly tied to specific physical work or materials but are essential for project execution.

These costs typically include items such as project management salaries, temporary site facilities (like trailers and toilets), utilities for the construction site, insurance, permits, and safety measures. By financing these elements, general conditions help to ensure that the project runs smoothly and effectively, allowing the direct labor and materials to be efficiently organized.

The other options focus on very specific aspects of a construction project. Direct labor costs represent wages directly linked to construction work, while subcontractor costs are limited to those incurred by third-party specialists. Material procurement costs pertain to the purchasing of physical items for the project and do not encompass the broader management and administrative expenses considered under general conditions.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy